You can schedule a one-off simulation to run at a specific time. This option is useful when you expect a third-party system to populate customer data at a certain time or you want to simulate on large amounts of customer data during off-peak hours to minimize memory consumption in your application.

  1. In the Pega Customer Decision Hub portal, click Simulation Testing.

  2. Open the simulation that you want to schedule and click Actions Schedule simulation .

    The simulation must be in the Execute or Review stage.
  3. In the Schedule run window, click the Calendar icon and select the year, month, day, and hour for the simulation to start.

  4. Click Apply.

    The simulation status changes to Open-Scheduled. You can cancel any scheduled run by clicking Cancel schedule.