Setting breakpoints

Click the Breakpoint buttonBreakpoint buttonto access the Breakpoint Configuration form. You can set breakpoints for specific steps in activities.

To set breakpoints in an activity:

  1. Use the Class Name list to select an Applies To class. Wait until the list displays in the window.
  2. Select an activity in this class.
  3. Complete the Where to Break field. Select the step before which you want processing to pause. Select at entry or 1 to break when the activity starts. To break for each step, choose all steps.
  4. Click  Set Break  . The form changes list the added breakpoint.

When a breakpoint is set for the activity, when you (or the selected requestor connection) starts this activity, the Tracer window acquires focus.

To resume processing after a break, click Continue Continue in the Tracer.

NoteIf you don't resume processing for an hour after a break, processing resumes automatically.

NoteYou can't review the clipboard when processing has reached a breakpoint, as the requestor being traced is paused. BURND 12/8/05 clinic

To remove a set breakpoint, in the Breakpoint Configuration form, check the Remove box and click  Remove .

Up Using the Tracer