You are here: Case management > Process modeling > Flows > Moving a case to a different stage

Moving a case to a different stage

You can use the Change Stage shape to move a case to a different stage in the case life cycle. By revisiting or skipping a stage, you can support out-of-sequence processing in a case.

Tip: To programmatically change the stage of a case, use the pxChangeStage activity.

  1. Add the Change Stage shape to the life cycle of your case.

  2. Click the Change Stage shape.

  3. Indicate which stage a case enters when the Change Stage shape is processed.

  4. Optional: To clean up unresolved work, select the Close open assignments from current stage on change check box.

    At run time, open assignments are resolved before the case leaves the current stage. All processes that originated from the stage, including supporting processes and excluding spin-off flows, are stopped.