A flow in draft mode is being used in UAT, but in Production environment gives an error stating that flow is in draft mode.


Error Messages



Draft flow cannot be executed


Steps to Reproduce

  1. Create a flow in draft and migrate it to UAT environment.
  2. Call the flow. Observe if the flow is executed.
  3. Migrate the same flow into Production.
  4. Again call the flow and the error appears.


Root Cause



A Draft-mode flow will execute in an environment where the Production level setting is less than 5.

Resolution



The UAT environment had a Production level of 4 while the Production environment had a level of 5.
This accounted for the different handling of the draft-mode flow rules in the two environments.

 

Published March 1, 2016 - Updated October 8, 2020

Was this useful?

66% found this useful

Have a question? Get answers now.

Visit the Collaboration Center to ask questions, engage in discussions, share ideas, and help others.

Did you find this content helpful?

Want to help us improve this content?

We'd prefer it if you saw us at our best.

Pega Community has detected you are using a browser which may prevent you from experiencing the site as intended. To improve your experience, please update your browser.

Close Deprecation Notice
Contact us