Support Article

Effort Capture Date not in line with Burn Down agent time zone

SA-38223

Summary



The date used for the Effort Capture Date in the PegaProjMgmt-Data-RemainingEffortTracking class should be in line with the time zone configured in the Burn Down agent named TrackRemainingEfforts.

Otherwise, the burn down graph will not display all the daily values.

Since sprints only display weekdays (Monday-Friday), the days will be shifted by one day, leaving Mondays blank and other days shifted by one.

Error Messages



Not Applicable

Steps to Reproduce

Observe the issue on the burn down graph.

Root Cause



This issue was determined to be a product enhancement request.


Resolution



An enhancement request, FDBK-19614, has been created for consideration by Pega Product Management.

Published May 18, 2017 - Updated June 30, 2017