Skip to main content

This content has been archived and is no longer being updated. Links may not function; however, this content may be relevant to outdated versions of the product.

Support Article

Graph does not start from Correct Date

SA-6581

Summary



Even though Data Page has correct start end and End Date. Graph is starting from one day before.

Date properties and Time properties should be treated as part of the operator's default timezone. Right now they are treaded as server timezone.

Error Messages



Graph does not start from Correct Date


Steps to Reproduce



1) Launch a local app server on a machine that is setup with a timezone of UTC-8
2) Log in to the server
3) Export from SLSthe reporting test application then import to the local server
4) Create a line auto chart based on data page D_ReportingdataList. Use .Date1 as the X-axis
5) Run the section
6) First date should be Sept 30th 2014, but it shows Sept 29th 2014



Resolution



To get out of the issue, there a work around:

Issue is with date property only so you can use .Text property like applying some formatting .Text = someformatfunction(.Date)


This issue is scheduled to be resolved in  ML 8

Published January 31, 2016 - Updated October 8, 2020

Was this useful?

0% found this useful

Have a question? Get answers now.

Visit the Collaboration Center to ask questions, engage in discussions, share ideas, and help others.

Did you find this content helpful?

Want to help us improve this content?

We'd prefer it if you saw us at our best.

Pega Community has detected you are using a browser which may prevent you from experiencing the site as intended. To improve your experience, please update your browser.

Close Deprecation Notice
Contact us