Signature Date is not populating in Pega 7.2.2 version

SA-34401

Summary



The Signature Date is not populating in Pega 7.2.2 version. When the user clicks to accept the signature control, it should populate the date of acceptance on other designated filed to display acceptance date.

Error Messages



Not Applicable

Steps to Reproduce

  1. Add a signature control.
  2. On accept run an activity to update the signature date to an input filed.

Root Cause



The user has a branch in their 7.18 system which contains changes in "pzpega_control_signature" JS. The changes are to execute a global callback method peag.ui.signature.acceptSignatureCallback and pega.ui.signature.clearSignatureCallback on every successful 'Accept' and 'Clear' of any signature.

This change is missing in 7.2.2.


Resolution



Apply Hotfix: HFix-32412