Support Article
Green tick mark appears on navigation pane of TreeNavigation
SA-15444
Summary
Green tick mark appears on navigation pane of TreeNavigation even there is error in assignment. Use TreeNavigation7 harness in the screen flow.
Call the validation from the post action. If there is a validation message on a particular step, system is showing green tick mark.
Error Messages
Not Applicable.
Steps to Reproduce
1. Use TreeNavigation7 harness in screen flow. Select Allow errors and Save.
2. In the last step select the start shape. Take a flow with three to four assignments.
3. Call the validation from the post action. If there is a validation error message on the current step, it still shows green tick mark on the assignment marking it as complete.
Root Cause
If there are multiple flowactions with same property and if those are using screen flow to capture data.
And also if there is any property error in any of the flow-actions, then it sets only the first flowaction with error property as error status, but other error properties are marked as success.
Resolution
Hotfix-23517 resolves the issue.
Hotfix-23517 has the updated rules to set all the flowactions with error property, which shows error status except for future flowactions.
Published January 31, 2016 - Updated October 8, 2020
Have a question? Get answers now.
Visit the Collaboration Center to ask questions, engage in discussions, share ideas, and help others.