Final Activity is not getting executed

SA-663

Summary



Application is processing 30,000 records CSV file through Service File rule.
After processing all the records from the file it is not executing the Final Activity.
At the same time when small amount of data like 50 records is uploaded in the file, Final Activity is getting executed.

Error Messages



Not Applicable 

Root Cause




It was observed that mode was set to : asynchronous. Hence the final activity was not being invoked. This is a known issue in 6.3sp1.
Suggested local change to customer that enable
the "Lock temporary file names" and "Persist Log-Service-File instances" options for process tab for all File Listeners.

Resolution



Issue is resolved through following local change:
enable
the "Lock temporary file names" and "Persist Log-Service-File instances" options for process tab for all File Listeners.

Published April 1, 2016 - Updated October 8, 2020

Was this useful?

0% found this useful

Have a question? Get answers now.

Visit the Collaboration Center to ask questions, engage in discussions, share ideas, and help others.

Did you find this content helpful?

Want to help us improve this content?

We'd prefer it if you saw us at our best.

Pega Community has detected you are using a browser which may prevent you from experiencing the site as intended. To improve your experience, please update your browser.

Close Deprecation Notice
Contact us