pxChangeStage is not working as expected

SA-19217

Summary



Calling pxChangeStage in one of the activity to change the stage of the assignment, is throwing flow not found error. Due to this data is not committed.

Error Messages


Flow not found exception


Steps to Reproduce



1) Create a flow.
2) Change stage using pxChangeStage by calling it in an activity.
3) Observe the issue.


Root Cause



An issue in the custom application code. Developer is calling one of the custom activity in an incorrect steppage which inturn calling the pxChangeStage activity.

Resolution



Correct the step page reference to the Primary page (Engpg) to fix the issue.

 

Published February 9, 2016 - Updated October 8, 2020

Was this useful?

0% found this useful

Have a question? Get answers now.

Visit the Collaboration Center to ask questions, engage in discussions, share ideas, and help others.

Did you find this content helpful?

Want to help us improve this content?

We'd prefer it if you saw us at our best.

Pega Community has detected you are using a browser which may prevent you from experiencing the site as intended. To improve your experience, please update your browser.

Close Deprecation Notice
Contact us