Support Article

PMF agent TrackRemainingEfforts running at GMT not EST

SA-24719

Summary



It is observed in the PMF burndown chart that calculations occur on Tuesday, Wednesday, Thursday, Friday, and Saturday. The chart shows calculations are not occurring on Sunday and Monday. The anticipated days for the chart calculations are Monday, Tuesday, Wednesday, Thursday, and Friday.

The agent coupled to the population of the data in the chart is set to run at 10:30 PM EST and the node for the application is running in the Pega Cloud.


Error Messages

Not Applicable.


Steps to Reproduce

  1. Configure TrackRemainingEfforts to run at 10:30 PM EST on weekdays.
  2. Observe the report populated from TrackRemainingEfforts does not have any content for Monday.


Root Cause



A defect or configuration issue in the operating environment. Cloud systems run in GMT and as such the agent schedule and the server need to be configured to run on the same day to meet the intended business case. As 10:30 PM EST Monday is equivalent to 2:30 AM GMT Tuesday.

Resolution




Update the agent schedule according to the PDN article: https://pdn.pega.com/documents/project-management-framework-712-managing-burn-down-agent-technical-note

Block of interest:

Scheduled agent time, it is recommended that the time zone that the Agent run in should be set equivalent to the system's server time zone so that the burn down data is written correctly, which ensures that the burn down charts display the correct data. If Agent ends up running after midnight server time, some business days (Fridays) could be skipped because the server detects it as a non-business day. The burn down chart should run as late in the day as possible (before midnight) to capture the daily snapshot of remaining hours and points for the teams' work.

If the server time zone and the agent's time zone cannot line up exactly, the agent should be scheduled to fall on the same day as the server time. In other words, the agent should finish running before midnight on the server time.

Published August 23, 2017 - Updated December 2, 2021

Was this useful?

0% found this useful

Have a question? Get answers now.

Visit the Collaboration Center to ask questions, engage in discussions, share ideas, and help others.

Did you find this content helpful?

We'd prefer it if you saw us at our best.

Pega Community has detected you are using a browser which may prevent you from experiencing the site as intended. To improve your experience, please update your browser.

Close Deprecation Notice